Millennium Project – Multipurpose Convention Centre

Project Description

A major new facility to combine the functions of a Convention Centre, Conference Hall and Swazi Trade Promotion/Expo Centre with halls and meeting rooms of varying size and function.  GIBB was appointed to prepare a feasibility study on the project, identify the optimum location of the project in the Ezulwini Valley, prepare preliminary designs for the convention centre options, prepare construction cost estimates and prepare 20 years operating revenue.  Support was provided to GIBB by MEPD with the provision of relevant reports, documents and other data.  GIBB was requested to submit monthly progress reports describing the conduct of the work, actual progress versus planned progress, the contract’s financial situation, and recording any significant events and problems encountered during the reporting period as well as the action being taken to resolve these problems.

 

Client:Swaziland Government, Ministry of Economic Planning and Development
Location:Swaziland